Palma Springs Holiday Club & Spa - Phase ONE
Click above to view our latest newsletter |
This month’s announcement on the gallery page
We have now started digging the foundations of Block B, four weeks later than expected, another delay caused by Bulgarian bureaucracy and out of our control. It is too early to say when this building will be completely finished but we expect mid Summer handover.
Tiling has started in Block C and we expect handover of this building to be February. Plastering of the building will start mid November.
Block A is well on the way and we exxpect to be at roof level early December and Act 14 issued. Block A is still on target to be ready for Summer 2009.
Zhenya Petrova
Owners Liaison
Палм-Спрингс Холидей клуб И Спа - первый этап
Посмотреть наш последний бюллетень |
В этом месяце объявил о галерее страницу
Мы уже начали рыть фундамент Блок B, четыре недели позже, чем ожидалось, другой задержки, вызванные болгарский бюрократии и вне нашего контроля. Пока еще слишком рано говорить, когда это здание будет полностью закончена, но мы рассчитываем на середину Летний сезон.
Пракладка началась в блоке C и мы рассчитываем на передачу этого здания, которое будет февраль. Штукатурные этого здания начнется середине ноября.
Мы oжудать блок А быть на уравне крыши начале Декебря и 14 Закона опубликован. Блок по-прежнему намерены быть готов летом 2009 года.
Женя Петрова
Владельцы связи